Dry Dock 5 Construction Progress: June 2026

JOINT BASE PEARL HARBOR-HICKAM, Hawaii — Construction continues on the Navy’s largest military construction project at Joint Base Pearl Harbor-Hickam, managed by Officer in Charge of Construction Pearl Harbor Naval Shipyard (OICC PHNSY).

Progress includes installation of the dewatering struts, completion of precast pile driving at the East Substation, ongoing land reclamation activities, the start of pump well tension pile installation on June 4, the beginning of North Cofferdam pile installation on June 25, continued construction of the fire water pump house, and installation of 893 of 1,305 crane rail piles as of June 25.

The project also reached a major milestone on June 7 with its largest concrete placement to date: approximately 1,900 cubic yards of underwater tremie concrete for the South Headwall.

Legal Disclaimer:

EIN Presswire provides this news content "as is" without warranty of any kind. We do not accept any responsibility or liability for the accuracy, content, images, videos, licenses, completeness, legality, or reliability of the information contained in this article. If you have any complaints or copyright issues related to this article, kindly contact the author above.

Share this page:

Advanced Search Options

Search for:

Search scope:

Type:

Search in:

Date range:

The last

Sort by:

Sign up for:

Hawaiian Industry Watch

The daily local news briefing you can trust. Every day. Subscribe now.

By signing up, you agree to our Terms & Conditions.